Nancy,
They only submitted one set. They know they are required to submit 3, but they could probably only get one off the printer and get it up here by 5:00. Carmen has called and let them
know they are required to submit 3.
See you a week from Monday.
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Bruce Grantham [mailto:bgrantham@gra-ce.net]
Sent: Friday, July 01, 2011 4:38 PM
To: Clay Barnett
Subject: RE: TCA Plan Review
Just remembered, Monday’s a holiday … we’ll get the plans on Tuesday.
From: Bruce Grantham
Sent: Friday, July 01, 2011 4:35 PM
To: 'Clay Barnett'
Cc: Chris Robinson; Nancy Cline
Subject: RE: TCA Plan Review
Clay: Of course, we’ll pick up the plans on Monday and I’ll look at them for you. Regards, Bruce
From: Clay Barnett [mailto:cbarnett@addisontx.gov]
Sent: Friday, July 01, 2011 4:33 PM
To: Bruce Grantham
Cc: Chris Robinson; Nancy Cline
Subject: TCA Plan Review
Bruce,
I am out next week and I understand that Chris is out as well. Chris was reviewing TCA for us. They have submitted their third review. The plans were changed to remove the loop road
and address the comments. I do not believe there were any other revisions. The comments from the last review are attached and the revised plans are at the front desk. I know that
our contract is out of funds, but I am sure we will find a way to take care of it if we can get these reviewed. Please let Nancy know if you can help us out.
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857