Lea, Here is the updated report for Belt Line including the $70,000 previously allocated to Brookhaven Club Streets. With no changes to the payables, the remaining balance for the project is $51,295. Thanks, Marisa From: Marisa Perry Sent: Friday, May 13, 2011 12:40 PM To: Lea Dunn Cc: Nancy Cline; Clay Barnett; Alison Ream; Ext_mail Tom Forrest; Randy Moravec Subject: Belt Line and 2008 Capital Projects - 4/30/11 Lea, Here are the progress reports for Belt Line and the 2008 capital projects through 4/30/2011. Belt Line – I have included the contracts for HNTB and R.H. Shackelford approved in April. With the outstanding contracts, we will be overspent by $18,705. 2008 Capital Projects – I have included the contracts for Kleinfelder and R.H. Shackelford approved in April. With the outstanding contracts for the storage tank, I am projecting a $950,000 re-allocation from the Addison Road project to cover the amount. Vitruvian and Spring Valley still appear on track. Please let me know if I can provide any additional information. Thanks and have a good weekend! Marisa Marisa Perry, CPA Financial Services Manager Town of Addison (972) 450-7064