All Work completed today Thursday August 4 - Unload trucks, weld cone on jigs and worked on ring beam. Anticipated schedule for next 5 days · Friday August 5 – Weld cone on jigs, hoist equipment to roof · Saturday August 6 – Weld cone on jigs · Sunday August 7 – Weld cone on jigs · Monday August 8 – Weld cone on jigs · Tuesday August 9 – Weld cone plates in place and weld cone on jigs Ron Mathis Landmark Structures Office 817.439.8888 • Fax 817.439.9001 rmathis@teamlandmark.com www.teamlandmark.com