All Work completed today Wednesday July 20 – Poured 2nd floor, worked on slab on grade Anticipated schedule for next 5 days: · Thursday July 21 – Pour slab on grade · Friday July 22 – Slab on grade · Saturday July 23 – no work · Sunday July 24 – Steel group move in · Monday July 25 – Unload trucks, start tank Ron Mathis Landmark Structures Office 817.439.8888 • Fax 817.439.9001 rmathis@teamlandmark.com www.teamlandmark.com