All Work completed today Wednesday July 21 – Poured slab on grade Anticipated schedule for next 5 days: · Friday July 22 – Slab on grade, mob in equipment for steel group · Saturday July 23 – No work · Sunday July 24 – Steel group move in · Monday July25 – Unload trucks · Tuesday July 26 – Install ring beam and start assembly of tank Ron Mathis Landmark Structures Office 817.439.8888 • Fax 817.439.9001 rmathis@teamlandmark.com www.teamlandmark.com