All Work completed today Wednesday July 6 – Worked on 2nd floor and slab on grade. Anticipated schedule for next 5 days: · Thursday July7 - Electrical rough in on slab on grade, work on 2nd floor · Friday July 8 – Electrical rough in, work on 2nd floor · Saturday July 9 – Backfill interior · Sunday July 10 – no work · Monday July 11 – Work on slab on grade Ron Mathis Landmark Structures Office 817.439.8888 • Fax 817.439.9001 rmathis@teamlandmark.com www.teamlandmark.com