All Work completed today Wednesday August 3 – Weld on ring beam and worked on cone plate on jig Anticipated work for next 5 days: · Thursday August 4 – Work on ring beam and weld cone on jig, unload trucks, set up welding jig. · Friday August 5 – Weld cone on jigs, Hoist equipment to top of pedestal · Saturday August 6 – Weld cone on jigs · Sunday August 7 – Weld cone on jigs · Monday August 8 – Weld cone on jigs Ron Mathis Landmark Structures Office 817.439.8888 • Fax 817.439.9001 rmathis@teamlandmark.com www.teamlandmark.com