All Work completed today August 17 – Hung and weld tier 1-2 in place, Weld tier 3-4 on jigs Anticipated schedule for next 5 days: · Thursday August 18 – Hang and weld tier 1-2 in place, weld tier 3-4 on jigs. · Friday August 19 – Weld tier 1-2 in place, weld tier 3-4 on jigs · Saturday August 20 – Weld tier 1-2 in place, weld tier 3-4 on jigs · Sunday August 21 – Weld tier 1-2 in place, weld tier 3-4 on jigs · Monday August 22 – Weld tier 1-2 in place, weld tier 3-4 on jigs Ron Mathis Landmark Structures Office 817.439.8888 • Fax 817.439.9001 rmathis@teamlandmark.com www.teamlandmark.com