All Work completed today August 30 - - Weld tank tier 1-2 in place, weld tier 3-4 in place, weld tier 5 on jigs Anticipated schedule for next 5 days: · Wednesday August 31 - - Weld tank tier 1-2 in place, weld tier 3-4 in place, weld tier 5 on jigs · Thursday September 1 - Weld tank tier 1-2 in place, weld tier 3-4 in place, weld tier 5 on jigs · Friday September 2 – Weld tank tier 5 on jigs · Saturday September 3 – Weld tank tier 5 on jigs · Sunday September 4 – No work Ron Mathis Landmark Structures Office 817.439.8888 • Fax 817.439.9001 rmathis@teamlandmark.com www.teamlandmark.com