All Work completed today June 25 – Installed 2nd floor beams Anticipated schedule for next 5 days: · Sunday June 26 – Install 2nd floor beams · Monday June 27 – Load out pedestal equipment. Plumbing, fire protection rough in, Install jig road · Tuesday June 28 – Electrical rough in and work on 2nd floor, install jig road · Wednesday June 29 – Work on 2nd floor · Thursday June 30 – Back fill S.O.G. Ron Mathis Landmark Structures Office 817.439.8888 • Fax 817.439.9001 rmathis@teamlandmark.com www.teamlandmark.com