Work Completed today Sunday July 17 – Interior backfill Anticipated schedule for next 5 days: · Monday July 18 – Slab on grade, Electrical · Tuesday July 19 – Slab on grade, electrical, plumbing · Wednesday July 20 – Pour 2nd floor, slab on grade work, pour mechanical support and threshold · Thursday July 21 – Pour slab on grade · Friday July 22 – slab on grade Ron Mathis Landmark Structures Office 817.439.8888 • Fax 817.439.9001 rmathis@teamlandmark.com www.teamlandmark.com