All Work completed today June 24 – Installed ladders, safety climb and lighting protection. Removed tower and scaffold. Anticipated schedule for next 5 days: · Saturday June 25 – Install 2nd floor beams · Sunday June 26 – Prepare for plumber, electricians and fire protection. Get all material ready for Monday’s trucks · Monday June 27 – Load trucks. Plumbers, electricians and fire protection install under slab utilities. · Tuesday June 28 – Work on 2nd floor decking · Wednesday June 29 – Work on 2nd floor, jig road and interior backfill. Ron Mathis Landmark Structures Office 817.439.8888 • Fax 817.439.9001 rmathis@teamlandmark.com www.teamlandmark.com