All Work completed today August 15 – Weld tier 3-4 on jigs Anticipated schedule for next 5 days: · Tuesday August 16 – Hoist equipment to roof, Weld tiers 3-4 on jigs, x-ray. · Wednesday August 17 – Weld tiers 1-2 to ring beam, weld tier3-4 on jigs · Thursday August 18 – Weld tiers 1-2 to ring beam, Weld tiers 3-4 on jigs · Friday August 19 – Weld tiers 1-2 to ring beam, weld tiers 3-4 on jigs · Saturday August 20 – Weld tiers 1-2 , Weld tiers 3-4 on jigs Ron Mathis Landmark Structures Office 817.439.8888 • Fax 817.439.9001 rmathis@teamlandmark.com www.teamlandmark.com