All Work completed today July 19 – Electrical rough in, Plumbing rough in, poured mechanical support and threshold at double doors. Anticipated schedule for next 5 days: · Wednesday July 20 – Pour 2nd floor, Slab on grade rebar · Thursday July 21 – Pour Slab on grade · Friday July 22 – Slab on grade, load out · Saturday July 23 – Steel group mob in · Sunday July 24 - Steel group Ron Mathis Landmark Structures Office 817.439.8888 • Fax 817.439.9001 rmathis@teamlandmark.com www.teamlandmark.com