All Work completed today June 29 – Inspection of plumbing rough in, installed jig road and work on storage floor. Anticipated schedule for the next 5 days: · Thursday June 30 – Work on 2nd floor · Friday July 1 – Work on 2nd floor, install fire protection stub up · Saturday July 2 – Work on 2nd floor · Sunday July 3 – no work · Monday July 4 – no work Ron Mathis Landmark Structures Office 817.439.8888 • Fax 817.439.9001 rmathis@teamlandmark.com www.teamlandmark.com