Well, it looks like we will not be able to proceed with the Water Connection at Addison Rd & Sojourn. Pending availability of materials, we will have to look for another weekend where we can complete this work. Concerning our current excavation work, our foreman started late today & will not be able to confirm the existing main until Friday. He will plate the excavation at 3pm & will continue his work on Friday until the line is exposed and size / pipe type determined. Once complete, he will backfill the excavation & plate with asphalt patch until the fittings are available for installation. As soon as I have another update, I will let everyone know. Thanks, Claire Callaham CalHar Construction, Inc. 2138 CalHar Drive Melissa, Texas 75454 Office: 972-838-2888 Fax: 972-838-2299 Mbl: 214-325-1879 E-Mail: ckcallaham@calhar.com