I would like to thank everyone for a job well-done yesterday. Too bad the rains came when they did. Just a reminder that the cross and valves need to be pressure tested, either 150 psi for 4 hours or 200 psi for 2 hours. The welds have been tested to system pressure, as agreed. This test could be facilitated from the line to the east, as there is a blow-off there already. The three valves – north, west, and south should be shut. This process would again kill the north end of the Addison Rd line, so it should be scheduled to accommodate the restaurant, daycare, and the office building, most likely late night, overnight, or early morning. It may be advisable to complete this prior to final paving of Addison Rd. Please advise as to your schedule of this testing. Thanks again. David E. Wilde Town of Addison Public Works Inspector 972-450-2847 dwilde@addisontx.gov P Please consider the environment before printing this email. -----Original Message----- From: Johnathon Grammer [mailto:jgrammer@rogers-obrien.com] Sent: Thursday, November 12, 2009 12:16 PM To: Clay Barnett; David Wilde Cc: Carson Coleman Subject: Methodist Water Line Tap Meeting Clay and David, We are going to have a meeting at 2pm today in our trailer with the utility contractor to review any last questions about the water line tap on Addison Road. We would greatly appreciate it if you could attend and help facilitate questions. Please give me a call on my cell phone at 214-683-6744. Thank you. Johnathon Grammer Office Engineer Main 972.248.0411 ext 208 Fax 972.248.0562 Rogers-O’Brien Construction Dallas | Austin www.rogers-obrien.com