Lea, Thank you for taking Change Order #4 to be executed. The changes are necessary based on the revisions prepared by Icon Consulting Engineers for the Vitruvian Park Public Infrastructure, Phase 1B. Although this change order is for $24,236 bringing the revised contract amount to $5,719,747.55, it is less than the $5,954,740 that was authorized by council on April 28, 2009. If you have any questions, please let me know. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857