Bruce, Following are the items we are disputing with the December 13, 2009 Invoice: 1. Remove payment for the CLOMR until such time as it has been submitted. 2. Preparation of addendums and answering contractor’s questions should not be included as Construction Phase Services. These services are rendered after a contract has been signed with the contractor. Remove these costs from this item. 3. Remove $2,050 from Addn. Services No. 3. These additional services were capped at $28,950 for design services with the remaining $9,800 for Construction Phase Services. Since these will not be constructed, the Town of Addison cannot submit payment for services that were not rendered. 4. Remove all structural related payments until such time as the bridge design is finalized. Should you have any questions, please feel free to contact me. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857