Andy, Pay Application 3 is attached. Please have it executed and forward for payment. By the way, I am holding off on payment of this item until the execution of the two change orders: 1. 10" PVC SS PIPE (14'-16' DEEP) BY OPEN CUT 120 LF The following item will need to be added to Change Order #3 (Bruce, please add these if they are not included in Change Order #1 or #2): 1. LOWERING EXIST 8" WATER LINE 1 EA 2. 12" STEEL CASING BY BORE 30 LF I am unsure that the following item is a City expense: 1. PLATFORM FOR TEMP DUCT BANK SUPPORT 1 LS If you have any questions, please feel free to contact me. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 P Please consider the environment before printing this email.