Eric, Just a reminder that the project time ends on Sunday, June 13, 2010. The only unresolved issue that will suspend the contract time will be the illuminated street name signs. All other portions of the contract, including street signs and striping, should be completed before this date. Items that are going to be removed and added to the park contract must be completed by change order by Friday. A walkthrough should be scheduled for early this week in order to have time to complete the items on the punchlist before Friday, since we will not be conducting a walkthrough on Sunday, unless it is obvious that the contractor is not yet ready for a walkthrough. If you have any questions, please feel free to contact me. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857