Andy, This is included in Change Order 4 that was sent previously. If you have any questions, please let me know. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 -----Original Message----- From: Andrew Nord [mailto:anord@ntexcon.com] Sent: Thursday, December 17, 2009 10:51 AM To: 'Joel Massey' Cc: 'Andrew Rolph'; 'Bruce Dunne'; Clay Barnett; 'Zach Fusilier' Subject: RE: Email #2 - Updated Plans 7.9.09 Joel / Clay We are going to have JRJ Paving begin installing this sidewalk under the assumption that Joel’s email below is proper authorization and approval for the provided price for this work. If this is incorrect, please let me know and I will have JRJ stop immediately, but we do need to get this sidewalk installed as to not hold up the project in any other way. Thanks Andy Nord Cell: 817.819.4117 Email: anord@ntexcon.com From: Joel Massey [mailto:jmassey@icon-engineers.com] Sent: Tuesday, December 15, 2009 8:25 AM To: Andrew Nord Cc: Andrew Rolph; Bruce Dunne Subject: RE: Email #2 - Updated Plans 7.9.09 Andy, Proceed with this change order for adding the “Joint Detail for Sidewalk Adjacent to Curb” for a distance of 600 LF at $10.03 / LF for a total of $6018.00. We will add to CO4. Joel A. Massey Project Manager icon Consulting Engineers, Inc. Bicentennial Financial Center 250 W. Southlake Blvd., Suite 117 Southlake, Texas 76092 Phone: (817) 552-6210 Fax: (817) 552-3126 Mobile: (817) 229-7944 jmassey@icon-engineers.com From: Andrew Nord [mailto:anord@ntexcon.com] Sent: Friday, December 11, 2009 12:26 PM To: Joel Massey Subject: FW: Email #2 - Updated Plans 7.9.09 Joel Here is our quote for the added work on the sidewalks at the back of curb. JRJ Price / LF 8.93 10% NTC markup on sub 0.90 2% Bonding adjustment 0.20 TOTAL UNIT PRICE $10.03 / LF Let me know if this is acceptable and I will tell Drew to get this work done. I will supply this price with the rest of the change order 4 pricing. Andy Nord Cell: 817.819.4117 Email: anord@ntexcon.com From: Marty Murphy [mailto:Martym@JRJPaving.com] Sent: Friday, December 11, 2009 11:23 AM To: Andrew Nord Subject: RE: Email #2 - Updated Plans 7.9.09 The cost for the dowel, concrete lug and joint sealer at back of curb to move the sidewalk to back of curb for 600 lf is $ 8.39/lf please forward a change order for this work so we may proceed. From: Andrew Nord [mailto:anord@ntexcon.com] Sent: Friday, July 10, 2009 10:10 AM To: Marty Murphy; 'David Whitaker'; 'Inlet Structure Specialties'; wcissacson@yahoo.com Cc: 'Zach Fusilier'; arolph@ntexcon.com; 'Craig Benckendorf' Subject: Email #2 - Updated Plans 7.9.09 Andrew D. Nord North Texas Contracting | Estimator 4999 Keller Haslet Rd. Keller, TX 76248 Phone: 817.430.9500 Fax: 817.430.9207 Cell: 817.819.4117