Bill,
Attached is the detail I had sent Joel. I stole it from Carrollton. Is there something that would work better?
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
-----Original Message-----
From: Bill Campbell [mailto:owcampbell@kleinfelder.com]
Sent: Wednesday, March 31, 2010 2:01 PM
To: Clay Barnett
Subject: Re: FW: VP Phase 1B Infra - Add Storm Drain Inlet
It is possible. Do you have a detail that I can look at?
I have attached a detail from another product that I have seen.
Bill Campbell, Jr., P.E.
North Texas Area Manager
2035 Central Circle #110
McKinney, TX 75069
o| 972.562.4677
c| 214.837.4476
f| 972.542.4366
>>> Clay Barnett 3/31/2010 1:40 PM >>>
Bill,
Do you think the rock needs to go all the way to the surface or is there a point at which we can begin to fill with native material?
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
-----Original Message-----
From: Andrew Nord [mailto:anord@ntexcon.com]
Sent: Monday, March 22, 2010 2:49 PM
To: 'Nick Jacob'; arolph; zackf; Clay Barnett; 'Joel Massey'
Cc: 'Eric T. Little'
Subject: RE: VP Phase 1B Infra - Add Storm Drain Inlet
Nick
Attached is the pricing for the under drain and our material pricing backup. Please note that almost half of the price for this work is the full depth rock backfill. If we would eliminate
this backfill and only do a foot or two of rock, the pricing would be significantly cheaper.
Thanks and let me know if you have any questions.
Andy Nord
Cell: 817.819.4117
Email: anord@ntexcon.com
From: Nick Jacob [mailto:PJacob@udr.com]
Sent: Wednesday, March 17, 2010 10:04 AM
To: Andrew Nord; 'Victor Marshall'; arolph; zackf
Cc: Eric T. Little
Subject: RE: VP Phase 1B Infra - Add Storm Drain Inlet
Andy,
Attached is the detail for the subsurface drain.
Thanks,
Nick
________________________________
From: Andrew Nord [mailto:anord@ntexcon.com]
Sent: Wednesday, March 17, 2010 6:21 AM
To: 'Victor Marshall'; arolph; zackf
Cc: Nick Jacob; Eric T. Little
Subject: RE: VP Phase 1B Infra - Add Storm Drain Inlet
Can we get a copy of the detail for the subsurface drain? Also, can we get a linear footage that is to be installed? Are we to install a storm drain inlet with this as well?
Andy Nord
Cell: 817.819.4117
Email: anord@ntexcon.com
From: Victor Marshall [mailto:vmarshall@ntexcon.com]
Sent: Tuesday, March 16, 2010 11:24 AM
To: Andrew Nord; 'Andrew Rolph'; Zach Fusilier
Subject: FW: VP Phase 1B Infra - Add Storm Drain Inlet
From: Nick Jacob [mailto:PJacob@udr.com]
Sent: Tuesday, March 16, 2010 9:27 AM
To: 'vmarshall@ntexcon.com'
Subject: Fw: VP Phase 1B Infra - Add Storm Drain Inlet
See below
________________________________
From: Joel Massey
To: Clay Barnett ; Nick Jacob
Cc: Bruce Dunne ; Eric T. Little
Sent: Tue Mar 16 08:26:19 2010
Subject: RE: VP Phase 1B Infra - Add Storm Drain Inlet
Ok Clay.
Nick, Please contact North Texas Contracting and provide us a price, per L.F., for the Town’s “Subsurface Drain Detail”.
Joel A. Massey
Project Manager
icon Consulting Engineers, Inc.
Bicentennial Financial Center
250 W. Southlake Blvd., Suite 117
Southlake, Texas 76092
Phone: (817) 552-6210
Fax: (817) 552-3126
Mobile: (817) 229-7944
jmassey@icon-engineers.com
From: Clay Barnett [mailto:cbarnett@addisontx.gov]
Sent: Tuesday, March 16, 2010 9:13 AM
To: Joel Massey
Cc: Nick Jacob; Bruce Dunne; Eric T. Little
Subject: RE: VP Phase 1B Infra - Add Storm Drain Inlet
Joel,
When we visited the project site the borings were deemed to not be necessary. The top of the tan weathered limestone is approximately 4-5 feet deep in spite of what the geotechnical
report indicates. Please make the necessary changes as quickly as possible. We need to get this situation resolved.
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
-----Original Message-----
From: Joel Massey [mailto:jmassey@icon-engineers.com]
Sent: Thursday, March 11, 2010 2:42 PM
To: Clay Barnett
Cc: Nick Jacob; Bruce Dunne; Eric T. Little
Subject: RE: VP Phase 1B Infra - Add Storm Drain Inlet
Clay,
The roadway borings in this area (i.e. P-2 at Park Road) do not indicate any weathered limestone or ground water to a depth of ten feet. The weathered limestone begins near the top
of the hill (Ponte Ave.). I recommend we do the subsurface investigation work before we decide what is needed.
Joel
From: Clay Barnett [mailto:cbarnett@addisontx.gov]
Sent: Thursday, March 11, 2010 2:21 PM
To: Joel Massey
Cc: Nick Jacob; Bruce Dunne; Eric T. Little
Subject: RE: VP Phase 1B Infra - Add Storm Drain Inlet
Joel,
Attached is a detail we got from the City of Carrollton for the subsurface drain. We need to run the drain from the inlet located at Sta. 6+65 to approximately Sta. 13+00. This will
be added to the Phase 1B contract and can be included in Change Order 6 which is the removal of all the items that cannot be constructed prior to May 31 due to the delay in the bridge
package. We will add the extension of the 18” RCP up to the right-of-way or drainage easement (if there is one) to the Phase 1B contract as well. Beyond that point we will either need
to acquire a drainage easement or UDR will need to perform the work.
If you have any questions, please feel free to contact me.
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
-----Original Message-----
From: Joel Massey [mailto:jmassey@icon-engineers.com]
Sent: Thursday, March 11, 2010 1:43 PM
To: Eric T. Little
Cc: Nick Jacob; Clay Barnett; Bruce Dunne
Subject: RE: VP Phase 1B Infra - Add Storm Drain Inlet
Ok Eric.
I will need direction from you and Clay for two items:
1. The extent and location of the “paving subsurface drainage”. (after the condition is determined)
2. Whether or not these revisions are to be added to Phase 1B contract and drawings or something else.
Joel
From: Eric T. Little [mailto:ELittle@udr.com]
Sent: Thursday, March 11, 2010 1:31 PM
To: Joel Massey; Bruce Dunne; Clay Barnett
Cc: Nick Jacob
Subject: FW: VP Phase 1B Infra - Add Storm Drain Inlet
Joel,
I’m good to go with this. Clay is going to send you a copy of the town’s detail for the paving subsurface drainage that they are wanting to add.
Thanks,
Eric Little
Project Manager, UDR
5430 LBJ Freeway, Suite 1250
Dallas, TX 75240
Ph: 972.774.0552
Fx: 972.991.4113
Cell: 214.641.5761
www.UDR.com
From: Joel Massey [mailto:jmassey@icon-engineers.com]
Sent: Thursday, March 11, 2010 1:05 PM
To: Eric T. Little
Cc: cbarnett@addisontx.gov; Bruce Dunne
Subject: VP Phase 1B Infra - Add Storm Drain Inlet
Eric,
Per our meeting yesterday at the site, attached is an exhibit showing our recommendation for collecting the storm water runoff north of the northeast corner of Vitruvian Way and Park
Road. The second exhibit contains the same information as the first but has been extended to the north so that you may see the original site conditions upstream.
The drop inlet shown has been located based on the extension of the now existing 18” RCP storm drain stub-out, Line D4.1, and the relocated AT&T underground telephone cable (labeled
UGT on the exhibit) in this area. We do not have any survey information as to the location of any of the now new features in this area (e.g. fencing, drainage channel, trees, irrigation,
electrical, etc). If this storm drain inlet is to be installed, it will need to be coordinated with the existing features.
It is my understanding that the Town has directed further subsurface investigation for any other subsurface water issues in this area. Please let me know if we need to provide any additional
services for this item or if any additional construction drawings are needed.
Joel A. Massey
Project Manager
icon Consulting Engineers, Inc.
Bicentennial Financial Center
250 W. Southlake Blvd., Suite 117
Southlake, Texas 76092
Phone: (817) 552-6210
Fax: (817) 552-3126
Mobile: (817) 229-7944
jmassey@icon-engineers.com
******************************************************************************************************************
This e-mail and any files or attachments transmitted with it contains Information that is confidential and privileged. This document may contain Protected Health Information (PHI) or
other information that is intended only for the use of the individual(s) and entity(ies) to whom it is addressed. If you are the intended recipient, further disclosures are prohibited
without proper authorization. If you are not the intended recipient, any disclosure, copying, printing, or use of this information is strictly prohibited and possibly a violation of
federal or state law and regulations. If you have received this information in error, please delete it and notify Hamid Khaleghipour at 972-450-2868 immediately. Thank you.
*******************************************************************************************************************
Warning: Information provided via electronic media is not guaranteed against
defects including translation and transmission errors.
If the reader is not the intended recipient, you are hereby notified that any
dissemination, distribution or copying of this communication is strictly
prohibited. If you have received this information in error, please notify the
sender immediately.