Great. Also, make sure the single phase transformer pad is in the correct location and grade. Joel From: Andrew Rolph [mailto:arolph@ntexcon.com] Sent: Wednesday, February 24, 2010 8:50 AM To: Joel Massey Cc: pjacob@udr.com; wgeistweidt@kleinfelder.com; Bruce Dunne; cbarnett@addisontx.gov; elittle@udr.com Subject: RE: File upload notification for Vitruvian Infrastructure Phase 1B We have a meeting set up with ForceCon and Oncor this Friday from 9:30-10am to discuss re-leveling the existing switchgear pad in service. ForceCon will be leveling the others starting today as they have now wrapped up their remaining scope. Thanks, Andrew D. Rolph North Texas Contracting 4999 Keller Haslet Rd. Keller, TX 76248 (O) 817-430-9500 (F) 817-430-9207 (M) 817-819-0703 From: Joel Massey [mailto:jmassey@icon-engineers.com] Sent: Wednesday, February 24, 2010 7:39 AM To: arolph@ntexcon.com Cc: pjacob@udr.com; wgeistweidt@kleinfelder.com; Bruce Dunne; cbarnett@addisontx.gov; elittle@udr.com Subject: RE: File upload notification for Vitruvian Infrastructure Phase 1B Andrew, What is the schedule of getting this equipment area finalized? The need for the single phase transformer (connected to the existing switchgear) is quickly approaching. Please let me know. Joel From: Joel Massey Sent: Wednesday, January 27, 2010 9:59 AM To: arolph@ntexcon.com Cc: pjacob@udr.com; wgeistweidt@kleinfelder.com; Bruce Dunne; cbarnett@addisontx.gov; Eric Little (elittle@udr.com) Subject: RE: File upload notification for Vitruvian Infrastructure Phase 1B Andrew, As a follow up to our telephone conversation this morning, the electric utility equipment pads south of Park Road need to be corrected for grade. ALL equipment pads must be level, at least 3 inches above the adjacent top of curb and located per the detailed exhibits previously provided (and included below). Additionally, the single phase transformer pad appears to be located too close to the 5 Way Switchgear pad. As indicated below, there are existing easements in place and required future landscaping in this area between each of these equipment pads. Please let me know if you need any additional information. Joel A. Massey Project Manager icon Consulting Engineers, Inc. Bicentennial Financial Center 250 W. Southlake Blvd., Suite 117 Southlake, Texas 76092 Phone: (817) 552-6210 Fax: (817) 552-3126 Mobile: (817) 229-7944 jmassey@icon-engineers.com From: jmassey@icon-engineers.com [mailto:jmassey@icon-engineers.com] Sent: Friday, August 21, 2009 11:21 AM To: arolph@ntexcon.com; Joel Massey; pjacob@udr.com; shines@jbipartners.com; jhaynes@udr.com; wgeistweidt@kleinfelder.com; Bruce Dunne; dburns@udrt.com; mbrendel@udr.com; cbarnett@addisontx.gov Subject: File upload notification for Vitruvian Infrastructure Phase 1B Special Comments: The utility equipment in the area of Park Road and Vitruvian Way is very tight (as are all of the other utility equipment areas) and probably needs the attached Detailed Exhibits. There are required landscaping (trees) to be planted in this area and the utility equipment must be located as close to intended as possible. Please make sure that this utility equipment area is constructed per the detailed plan. ________________________________ New Files Uploaded As of 21-Aug-2009 11:20 AM CT Vitruvian Infrastructure Phase 1B 4010 Marsh Lane Addison, Texas 75001 Project Number: 1308B The following files were added to your project web. Login to the project to access the files OR click on the filename to download one file at a time. NOTE: The email link below only opens the LATEST version of the file. Tab: Construction Menu: 4-Drawings Folder: 1B - Paving, Drainage & Utility Imp- BCD & PA Folder: Construction Folder: Exhibits Folder: Park Road & Vitruvian Way - Detailed Utility Plan File(s): XBP1cSDUP1o2.pdf (91552 bytes) XBP1cSDUP2o2.pdf (68281 bytes) .................................................................................. Copyright (c) 1999-2009, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - Blueprint for e-Management