I am sending Ramon right away to pump this water off. Thanks for the info on the breaks. Andrew D. Rolph North Texas Contracting 4999 Keller Haslet Rd. Keller, TX 76248 (O) 817-430-9500 (F) 817-430-9207 (M) 817-819-0703 From: Wade Geistweidt [mailto:wgeistweidt@kleinfelder.com] Sent: Monday, March 22, 2010 3:49 PM To: arolph@ntexcon.com Cc: cbarnett@addisontx.gov; elittle@udr.com; pjacob@udr.com Subject: PONDING WATER Andrew, Ramons crew fixed the inlet at station 10+30. However they did not do anything with the ponding water at the driveway for the job trailers. This water needs to be removed from the paving subgrade so JRJ can have dry subgrade to pour the leave out at this location. Also the three day average for the concrete poured on Friday 3-19-10 came back with 4133psi average break. Clay has been notified of this and is ok with JRJ getting there construction equipment on the new concrete at this time. Thanks Wade Warning: Information provided via electronic media is not guaranteed against defects including translation and transmission errors. If the reader is not the intended recipient, you are hereby notified that any dissemination, distribution or copying of this communication is strictly prohibited. If you have received this information in error, please notify the sender immediately.