Zach,
I am fine with the pricing. Given this information, I assume the 20 days for construction is a typo?
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Zach Fusilier [mailto:zfusilier@ntexcon.com]
Sent: Tuesday, April 20, 2010 3:10 PM
To: Clay Barnett
Cc: 'Eric T. Little'; 'Nick Jacob'; anord; mikesr@ntexcon.com; 'Jennifer Haynes'; 'Bruce Dunne'; arolph; Nancy Cline
Subject: RE: Revised Sewer Pricing
Clay,
We can compromise on this issue in an effort to get where we can all agree. I know how important this is to the City. I cut all the funds for the existing utilities and the gas station
out. Based on our estimated and documented production on the job we need to finish the sewer in 3 days to be under budget. By adding the Spring Valley crossing we believe the best
case duration is 6 days from start to finish with 4 days being in the road just because we go lane by lane. I have only left 3 days for spring valley, the remobilization and the added
cost for trench repair since the width is so narrow and its in a major street done lane by lane. This is almost 50 % of what the bore would have cost and our original pricing so the
City and UDR are getting a good deal and meeting the deadline. I also assume the CO will add the CTB encasement per the contract unit. Please review and let us know. This is the cheapest
we can go without losing money on this change. Please let me know.
Zach Fusilier
North Texas Contracting
4999 Keller Haslet Road
Keller, Texas 76248
Office - 817-430-9500
Cell - 817-819-6691
From: Clay Barnett [mailto:cbarnett@addisontx.gov]
Sent: Tuesday, April 20, 2010 1:41 PM
To: zackf
Cc: Eric T. Little; Nick Jacob; anord; mikesr@ntexcon.com; Jennifer Haynes; 'Bruce Dunne'; Andrew Rolph; Nancy Cline
Subject: RE: Revised Sewer Pricing
Zach,
I concur with Bruce that the sewer across Spring Valley is more difficult and will result in extra costs and the Town is fine with that. However, the sewer south of Spring Valley is
no different than what was placed in the rest of Vitruvian. The gas station and canopy will be demolished immediately following the installation of the sewer line, so destroying it
early should not be a concern. Also, the only lines that run to the building on the side the sewer line is coming from is the emergency shutoff for the pumps. The trench can be seen
in the parking lot. Power has been killed, so this also will not be an issue. Please consider installing the sewer up to Spring Valley for the price that is in the contract as we discussed
a few weeks ago. If this is not going to happen, please let me know ASAP.
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Bruce Dunne [mailto:bdunne@icon-engineers.com]
Sent: Tuesday, April 20, 2010 1:21 PM
To: Andrew Rolph; zackf
Cc: Eric T. Little; Nick Jacob; anord; mikesr@ntexcon.com; Jennifer Haynes; Clay Barnett
Subject: RE: Revised Sewer Pricing
This is entirely up to Clay on whether to accept your change order. I have left him several messages but have not heard from him today. Andrew – you may want to run by his office and
try to find him and discuss this change order with him.
________________________________
From: Andrew Rolph [mailto:arolph@ntexcon.com]
Sent: Tuesday, April 20, 2010 12:08 PM
To: zackf; Bruce Dunne
Cc: 'Eric T. Little'; 'Nick Jacob'; anord; mikesr@ntexcon.com; 'Jennifer Haynes'; 'Clay Barnett'
Subject: RE: Revised Sewer Pricing
Gentlemen, I will need to have formal approval in order to start this sewer extension tomorrow. As of right now, I have trucks set up to mobilize my crew and equipment… If I don’t
hear anything back by 2 pm I will have to cancel the haul trucks so I don’t incur unnecessary costs. I know there is a lot of pressure from the school district to have this work complete
by the 1st so please let me know a.s.a.p.
Thanks,
Andrew D. Rolph
North Texas Contracting
4999 Keller Haslet Rd.
Keller, TX 76248
(O) 817-430-9500
(F) 817-430-9207
(M) 817-819-0703
From: Zach Fusilier [mailto:zfusilier@ntexcon.com]
Sent: Tuesday, April 20, 2010 8:50 AM
To: 'Bruce Dunne'
Cc: 'Eric T. Little'; 'Nick Jacob'; anord; arolph; mikesr@ntexcon.com; 'Jennifer Haynes'; 'Clay Barnett'
Subject: RE: Revised Sewer Pricing
Bruce,
I have revised the additional charge for the sewer through the gas station from 1.5 days to .5 days. The sewer that runs between the canopy and the building will be extremely difficult
as to not damage existing items and avoid obstructions. It is also anticipated that the entire area around the tanks will be pea gravel and subject to sloughing, etc… See if this is
more reasonable and let us know. We are hesitant to believe that there will only be one telephone crossing through the parking lot, but we’ll see. Thanks
Zach Fusilier
North Texas Contracting
4999 Keller Haslet Road
Keller, Texas 76248
Office - 817-430-9500
Cell - 817-819-6691
From: Bruce Dunne [mailto:bdunne@icon-engineers.com]
Sent: Tuesday, April 20, 2010 8:28 AM
To: Zach Fusilier
Cc: Eric T. Little; Nick Jacob; anord; arolph; mikesr@ntexcon.com; Jennifer Haynes; Clay Barnett
Subject: RE: Revised Sewer Pricing
I do not disagree with you on the work across Spring Valley and have no problem with the additional shoring and utility crew days for the street crossing at Spring Valley Road. What
I am saying is (in my opinion) the sewer work in Vitruvian Way and across the Gas Station property (with the only utility crossing in this area being a underground telephone line 5’
above the sewer line) is no different than what you installed previously.
________________________________
From: Zach Fusilier [mailto:zfusilier@ntexcon.com]
Sent: Tuesday, April 20, 2010 8:26 AM
To: Bruce Dunne
Cc: 'Eric T. Little'; 'Nick Jacob'; anord; arolph; mikesr@ntexcon.com; 'Jennifer Haynes'; 'Clay Barnett'
Subject: RE: Revised Sewer Pricing
Bruce,
The unit prices in our contract were for sewer that was far less difficult and thus cheaper to install. It will take 4-5 days to install a few hundred feet through the gas station and
across spring valley. We cannot do the sewer across spring valley while crossing 4-5 major utilities for the same prices we have in place for sewer down a closed side of Vitruvian.
We priced Vitruvian sewer and on many days laid 150-250 LF per day. We will spend a minimum of 3 days in Spring Valley to lay 75 LF. It is also important for everyone to remember
that this was originally to be bored. I solicited seven subcontractor’s to price the bore and the lowest out of the 5 that bid was $ 325 / LF no including bore pits. This would have
been a $ 30,000 addition on top of the sewer costs. The City and UDR is not only saving money by open cutting but they are also getting the sewer I by the end of the month. This being
factored along with the savings from the original bore installation I hope will prove reasonable.
Zach Fusilier
North Texas Contracting
4999 Keller Haslet Road
Keller, Texas 76248
Office - 817-430-9500
Cell - 817-819-6691
From: Bruce Dunne [mailto:bdunne@icon-engineers.com]
Sent: Tuesday, April 20, 2010 8:10 AM
To: Zach Fusilier
Cc: Eric T. Little; Nick Jacob; anord; arolph; mikesr@ntexcon.com; Jennifer Haynes; Clay Barnett
Subject: RE: Revised Sewer Pricing
Zach – there are unit prices established in the Phase 1B contract for all of the sewer depths as shown on the plans, and there is also a price established for CTB encasement, so these
are not additional services being provided. I also do not understand your request for additional compensation merely for utility crossing and for gas station crossing. Would you explain
your reasoning?
Clay and Eric – What are your thoughts regarding this additional request.
________________________________
From: Zach Fusilier [mailto:zfusilier@ntexcon.com]
Sent: Tuesday, April 20, 2010 7:05 AM
To: Bruce Dunne
Cc: 'Eric T. Little'; 'Nick Jacob'; anord; 'arolph'; mikesr@ntexcon.com; 'Jennifer Haynes'
Subject: Revised Sewer Pricing
Bruce,
Attached is the revised price based on the increased depth, CTB encasement and the crossing under the water line. Please let us know if approved so we can begin this morning or make
arrangements to work on the under drain instead that I believe is approved. Also, can you verify that CO # 6 will be approved soon as to allow for April billing on the items we are
completing. Can you update us on the retaining wall approval as well since we can begin this soon if approved. Thanks
Zach Fusilier
North Texas Contracting
4999 Keller Haslet Road
Keller, Texas 76248
Office - 817-430-9500
Cell - 817-819-6691
******************************************************************************************************************
This e-mail and any files or attachments transmitted with it contains Information that is confidential and privileged. This document may contain Protected Health Information (PHI) or
other information that is intended only for the use of the individual(s) and entity(ies) to whom it is addressed. If you are the intended recipient, further disclosures are prohibited
without proper authorization. If you are not the intended recipient, any disclosure, copying, printing, or use of this information is strictly prohibited and possibly a violation of
federal or state law and regulations. If you have received this information in error, please delete it and notify Hamid Khaleghipour at 972-450-2868 immediately. Thank you.
*******************************************************************************************************************