Attached is the revised CO#& as requested.
From: Clay Barnett [mailto:cbarnett@addisontx.gov]
Sent: Friday, July 23, 2010 8:34 AM
To: 'Eric T. Little'; Bruce Dunne; arolph
Cc: Nick Jacob; Zach Fusilier (zfusilier@ntexcon.com); Andy Nord (anord@ntexcon.com)
Subject: RE: Vit Park - Phase 1B - June Pay App and CO 7 adjustments
Eric, based on this information I have attached the final pay application.
Bruce, please send the revised CO#7 as quickly as possible.
Andrew, we will need the street lights repainted and the last two installed, the electrical work done, the Addison logo manhole covers installed and the illuminated street name signs
installed before we can issue final payment.
If anyone has any questions, please let me know.
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Eric T. Little [mailto:ELittle@udr.com]
Sent: Friday, July 23, 2010 9:00 AM
To: Clay Barnett
Cc: arolph; Nick Jacob; Bruce Dunne (bdunne@icon-engineers.com)
Subject: RE: Vit Park - Phase 1B - June Pay App and CO 7 adjustments
Clay:
#59 – 19,555 - Original Contract Value
920 – CO #2
<234> - CO #6
20,241 is correct
You are correct on CO#7 as well.
Eric Little
Project Manager, UDR
5430 LBJ Freeway, Suite 1250
Dallas, TX 75240
Ph: 972.774.0552
Fx: 972.991.4113
Cell: 214.641.5761
www.UDR.com
From: Clay Barnett [mailto:cbarnett@addisontx.gov]
Sent: Thursday, July 22, 2010 5:36 PM
To: Eric T. Little
Cc: arolph; Nick Jacob; Bruce Dunne (bdunne@icon-engineers.com)
Subject: RE: Vit Park - Phase 1B - June Pay App and CO 7 adjustments
Eric,
BID-59 should be 20241 I believe. Please verify.
On Change Order #7, we need to take 6 units out of Bid-269, because I believe there is an error in Change Order #1 (I think it should have been -3 instead of +3).
Thanks,
Clay Barnett, P.E.
Town Engineer
Town of Addison
16801 Westgrove Drive
Addison, TX 75001-2818
Office: (972) 450-2857
From: Eric T. Little [mailto:ELittle@udr.com]
Sent: Thursday, July 22, 2010 3:43 PM
To: Clay Barnett; Bruce Dunne (bdunne@icon-engineers.com)
Cc: arolph; Nick Jacob
Subject: Vit Park - Phase 1B - June Pay App and CO 7 adjustments
Clay,
Please see the attached corrections to the June pay app for 1B.
Bruce,
Per our meeting with Clay today, the following items need to be corrected on CO 7 ASAP:
Delete #65 - 6” Topsoil from 1B contract
Delete #96 – 7’ Type B Manhole from 1B contract
#244 – Change Plan Quantity to 21 to account for shaft added in CO #3. Keep the Revised Quantity the same at 22.
Thanks,
Eric Little
Project Manager, UDR
5430 LBJ Freeway, Suite 1250
Dallas, TX 75240
Ph: 972.774.0552
Fx: 972.991.4113
Cell: 214.641.5761
www.UDR.com
******************************************************************************************************************
This e-mail and any files or attachments transmitted with it contains Information that is confidential and privileged. This document may contain Protected Health Information (PHI) or
other information that is intended only for the use of the individual(s) and entity(ies) to whom it is addressed. If you are the intended recipient, further disclosures are prohibited
without proper authorization. If you are not the intended recipient, any disclosure, copying, printing, or use of this information is strictly prohibited and possibly a violation of
federal or state law and regulations. If you have received this information in error, please delete it and notify Hamid Khaleghipour at 972-450-2868 immediately. Thank you.
*******************************************************************************************************************