Andy, As you are aware all available funds for Phase 1B were transferred to Phase 1C at the completion of the project. Therefore, all additional funds would need to be subsidized by UDR. Additionally, Icon has stated that NTC was paid for this work. If NTC feels there is a claim, they will need to substantiate the claim and file it through UDR. If you have any additional questions, please let me know. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Andy Nord [mailto:andy@ntexcon.com] Sent: Tuesday, December 07, 2010 3:58 PM To: Clay Barnett Cc: 'Zach Fusilier' Subject: Vitruvian 1B - Duct Bank Quantity Verification Clay During our final project quantity sweep, we found a run of 4E6 duct bank that wasn’t paid. I think that this quantity might have gotten over looked in all of the changes that were being made by Icon during the project. The section that we feel was missed are the laterals coming out of the manhole located at STA 3+77.67 on plan sheet 81. These laterals add up to 50’ of 4E6 duct bank. NTC / ForceCon is asking that the city take a look at this over-sight and correct it. Thanks and let me know if you need anything else for me or would like to set up a meeting to look at this stuff in more detail Andy Andrew D. Nord North Texas Contracting | Estimator 4999 Keller Haslet Rd. Keller, TX 76248 Phone: 817.430.9500 Fax: 817.430.9207 Cell: 817.819.4117