Bruce, Could we get Change Order #5 changed to where the staking and plotting is rolled into the cost of the flexbase? Also, it appears that we are adding 52.7 tons of dry lime at a price of $253.89/ton. We are waiting on trucking tickets for the dry lime. Please make the changes to the change order and resend. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 -----Original Message----- From: Bruce Dunne [mailto:bdunne@icon-engineers.com] Sent: Monday, February 15, 2010 5:27 PM To: Clay Barnett Cc: Eric T. Little Subject: Vitruvian Phase 1B - Change Order No. 5 See attachment. Call if any questions. BRUCE F. DUNNE, P.E. President icon Consulting Engineers, Inc. Bicentennial Financial Center 250 W. Southlake Blvd., Suite 117 Southlake, Texas 76092 Phone: (817) 552-6210 Fax: (817) 552-3126 Mobile: (817) 707-9711