The pricing looks ok, however I don't see why we should add a full day for this little bit of work. Comments? ________________________________ From: Andy Nord To: 'Andy Nord' ; Eric T. Little Cc: zackf ; arolph ; 'Clay Barnett' ; jmassey@icon-engineers.com Sent: Tue Jun 08 13:07:16 2010 Subject: RE: Electrical Pull Box on Marsh - Change Order Request Eric, in conjunction with the pricing that I recently sent over, NTC requests to add one day to our contract for the additional work as every item now is on the critical path of project completion. Thanks again Andy Nord Cell: 817.819.4117 Email: anord@ntexcon.com From: Andy Nord [mailto:andy@ntexcon.com] Sent: Tuesday, June 08, 2010 1:58 PM To: 'Eric Little (elittle@udr.com)' Cc: zackf; arolph; 'Clay Barnett'; 'jmassey@icon-engineers.com' Subject: Electrical Pull Box on Marsh - Change Order Request Eric Attached to this email is a CO Request for the demolition of the existing pull box and re-installation of an electrical pull box with concrete apron down near Marsh Ln. Please let me know if you have any questions with regards to this. Thanks Andy Andrew D. Nord North Texas Contracting | Estimator 4999 Keller Haslet Rd. Keller, TX 76248 Phone: 817.430.9500 Fax: 817.430.9207 Cell: 817.819.4117