Clay - I will get Tom to sign this and email back since I'm on vacation this week. Thanks, ________________________________ From: Andy Nord To: 'Clay Barnett' ; Eric T. Little Cc: zackf ; arolph Sent: Mon Jul 12 10:08:24 2010 Subject: RE: Vitruvian - May Estimate Here you go. From: Clay Barnett [mailto:cbarnett@addisontx.gov] Sent: Monday, July 12, 2010 10:19 AM To: 'Eric T. Little' Cc: zackf; 'Andy Nord'; 'Andrew Rolph' Subject: RE: Vitruvian - May Estimate Eric, Attached is Pay Application 13 for Phase 1B. Please be advised that the following quantities were negative in this pay application: · Item 22: -2 · Item 65: -1015 · Item 117: -125 · Item 261: -219 · Item 269: -318 · Item 272: -1 · Item 273: -2 If these items are correct, please have it executed and returned to me. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Eric T. Little [mailto:ELittle@udr.com] Sent: Thursday, June 24, 2010 6:02 PM To: Clay Barnett Subject: Fw: Vitruvian - May Estimate Clay, The May estimate is finally correct. See Andrew's comments below and let me know when you would like to do the final-final-final walk on 1B. Thanks, ________________________________ From: Andrew Rolph To: Eric T. Little; zackf ; Nick Jacob Cc: bdunne@icon-engineers.com ; anord Sent: Thu Jun 24 16:35:51 2010 Subject: RE: Vitruvian - May Estimate Here you go. By the way, Metroplex will be onsite tomorrow to re-work all of the “bubbly striping”, we can expect signage to be installed early next week, Durable has re-adjusted banner arms/plumb poles and would like to request a pole walk (not the gay kind of pole walk, but a pole walk nonetheless…), Durable will have their pole paint touched up by early next too, pull boxes have been addressed, NTC is complete with our inlet rework, TOA logo storm lids should be ready on the 29th, cracks at Bella have been filled with epoxy, and foam under FH is cleaned and sealed. I believe the only hold up will be the 2 additional poles on order for the east end near Bella; Durable has reported a 2-3 week lead time for delivery from their supplier. One last thing, ForceCon is on board to finish their duct run starting next Tuesday or Wednesday at latest; this should just be a 2 day operation at most including cleanup. Thanks, Andrew D. Rolph North Texas Contracting 4999 Keller Haslet Rd. Keller, TX 76248 (O) 817-430-9500 (F) 817-430-9207 (M) 817-819-0703 From: Eric T. Little [mailto:ELittle@udr.com] Sent: Thursday, June 24, 2010 4:57 PM To: Andrew Rolph; zackf; Nick Jacob Cc: bdunne@icon-engineers.com; anord Subject: RE: Vitruvian - May Estimate Andrew/Zach: Bruce and I just finished going through your pay app and offer the following COMMENTS BELOW: Basically, you need to change #123, 125, 244 and 272 to the contracted amount and then bill for the overage once the CO 7 is approved. Everything else except #269 is ok. On that one, change #269 to 1131lf (contracted) and 1086lf (installed to date). Call me if you have any questions. Thanks, Eric Little Project Manager, UDR 5430 LBJ Freeway, Suite 1250 Dallas, TX 75240 Ph: 972.774.0552 Fx: 972.991.4113 Cell: 214.641.5761 www.UDR.com From: Andrew Rolph [mailto:arolph@ntexcon.com] Sent: Wednesday, June 16, 2010 6:51 PM To: Eric T. Little; zackf; Nick Jacob Cc: bdunne@icon-engineers.com; anord Subject: RE: Vitruvian - May Estimate #22 – change billing quantity to $0 – moving to park package - Agreed and changed OK #34 – change billing quantity to $0 – moving to park package – This item was completed as shown on sheet 16 in our 1B contract AGREE #37 – change billing quantity to $0 – moving to park package - This item was completed as shown on sheet 16 in our 1B contract AGREE #59 – overbilled – should be 18,630sf – Change order 6 shows the quantity to be 19,321? I believe our quantities are right through the 25th of last month… Where is this new reduction coming from? AGREE YOU ARE CORRECT #117 – overbilled – should be 1,472lf – Agreed and changed to reflect CO #6 OK #123 – overbilled – this will be addressed in the next CO, but we can bill over without an approved CO right now. – Add to CO#7 AGREE, BUT WE CANNOT BILL FOR A CHANGE ORDER THAT IS NOT APPROVED YET. REMOVE OVERAGE FROM PAY APP – BILL ON FINAL INVOICE. #125 – overbilled – this was on my list last month too – we need to resolve this overage. – This is total amount of pipe installed and tested on this project (includes the RCB). Please add the overage to CO #7. AGREE, BUT WE CANNOT BILL FOR A CHANGE ORDER THAT IS NOT APPROVED YET. REMOVE OVERAGE FROM PAY APP – BILL ON FINAL INVOICE. #244 – see below – correct contract amount is 20 not 21 as I stated – There are 22 total foundations on the project, this is why we had to order the two extra SL Type 4 light poles. Please approve and add to CO #7. AGREE, BUT WE CANNOT BILL FOR A CHANGE ORDER THAT IS NOT APPROVED YET. REMOVE OVERAGE FROM PAY APP – BILL ON FINAL INVOICE. #251 – overbilled – you billed for 88ea, contract has 86ea – Agreed and changed..type-O in my favor? Ha. OK #261 – overbilled – should be 1,186lf – There is actually 1241 LF installed to date. I believe the difference can be found on sheet 79. ForceCon installed this 4T4 to station 23+45 before the sheet was revised to stop at 23+03. The other difference comes from calculating stations and in field verification. Please review the duct bank plans. Just FYI, I believe this quantity was originally so high to account for some 4T4 shown on sheets 50-51. AGREE #269 – overbilled – not sure how I missed this one last month, but you are over on the contract quantity and this duct bank is not complete yet (pending piers). – This is a quantity bust on the plans. I sent you an email back when Jennifer and I addressed this bust for reference. Basically, the installed plan quantity is 1404 minus the 375 LF taken out now for the cul-de-sac. This makes a new contract quantity of 1029 minus the 45 Lf yet to be installed leaves 984 LF installed to date. ACTUALLY THERE IS 273LF IN THE CUL-DE-SAC. CHANGE YOUR BILLING TO 1131LF – THE REST WILL BE ADDED TO PHASE 1C. #272 – overbilled – should be 1ea – One installed at station 13+75 and the other at station 18+60. This additional 2 way manhole needs to be added to CO#7. AGREE, BUT WE CANNOT BILL FOR A CHANGE ORDER THAT IS NOT APPROVED YET. REMOVE OVERAGE FROM PAY APP – BILL ON FINAL INVOICE. #273 – overbilled – should be 31ea – Agreed and changed per CO #6. OK Please review and let me know if any further changes need to be made to this application. Please remember that I have not yet adjusted the amount shown for the “paid to date”. Thanks, Andrew D. Rolph North Texas Contracting 4999 Keller Haslet Rd. Keller, TX 76248 (O) 817-430-9500 (F) 817-430-9207 (M) 817-819-0703 From: Eric T. Little [mailto:ELittle@udr.com] Sent: Wednesday, June 16, 2010 9:46 AM To: arolph@ntexcon.com; Zach Fusilier (zfusilier@ntexcon.com); Nick Jacob Cc: bdunne@icon-engineers.com Subject: RE: Vitruvian - May Estimate Bruce found a couple more issues: #22 – change billing quantity to $0 – moving to park package #34 – change billing quantity to $0 – moving to park package #37 – change billing quantity to $0 – moving to park package #59 – overbilled – should be 18,630sf #117 – overbilled – should be 1,472lf #244 – see below – correct contract amount is 20 not 21 as I stated #251 – overbilled – you billed for 88ea, contract has 86ea #261 – overbilled – should be 1,186lf #272 – overbilled – should be 1ea #273 – overbilled – should be 31ea Thanks, Eric Little Project Manager, UDR 5430 LBJ Freeway, Suite 1250 Dallas, TX 75240 Ph: 972.774.0552 Fx: 972.991.4113 Cell: 214.641.5761 www.UDR.com From: Eric T. Little Sent: Tuesday, June 15, 2010 4:21 PM To: arolph@ntexcon.com; Zach Fusilier (zfusilier@ntexcon.com); Nick Jacob Cc: bdunne@icon-engineers.com Subject: FW: Vitruvian - May Estimate Andrew: Have a couple issues with the following items: #123 – overbilled – this will be addressed in the next CO, but we can bill over without an approved CO right now. #125 – overbilled – this was on my list last month too – we need to resolve this overage. #244 – overbilled – you billed for 22ea, contract has 21ea #251 – overbilled – you billed for 88ea, contract has 86ea #269 – overbilled – not sure how I missed this one last month, but you are over on the contract quantity and this duct bank is not complete yet (pending piers). Eric Little Project Manager, UDR 5430 LBJ Freeway, Suite 1250 Dallas, TX 75240 Ph: 972.774.0552 Fx: 972.991.4113 Cell: 214.641.5761 www.UDR.com From: Andrew Rolph [mailto:arolph@ntexcon.com] Sent: Monday, June 14, 2010 7:39 PM To: Eric T. Little Cc: Nick Jacob; zackf; anord Subject: Vitruvian - May Estimate Eric, here is our May estimate for your review. The only thing that I still need to modify is the amount NTC has been paid to date, but this will at least get you started on reviewing the quantities. Thanks, Andrew D. Rolph North Texas Contracting 4999 Keller Haslet Rd. Keller, TX 76248 (O) 817-430-9500 (F) 817-430-9207 (M) 817-819-0703 ⁴敹⁴摡番瑳摥琠敨愠潭湵⁴桳睯潦⁲桴⁥炓楡⁤潴搠瑡鑥മഊ吊慨歮ⱳ਍਍ഠഊ䄊摮敲⁷⹄删汯桰਍਍潎瑲⁨敔慸⁳潃瑮慲瑣湩൧ഊ㐊㤹‹敋汬牥䠠獡敬⁴摒മഊ䬊汥敬Ⱳ吠⁘㘷㐲സഊ⠊⥏㠠㜱㐭〳㤭〵രഊ⠊⥆㠠㜱㐭〳㤭〲ഷഊ⠊⥍㠠㜱㠭㤱〭〷ളഊ ਍਍牆浯›牅捩吠‮楌瑴敬嬠慭汩潴䔺楌瑴敬畀牤挮浯⁝਍敓瑮›敗湤獥慤ⱹ䨠湵⁥㘱‬〲〱㤠㐺‶䵁਍潔›牡汯桰湀整捸湯挮浯※慚档䘠獵汩敩⁲稨畦楳楬牥湀整捸湯挮浯㬩丠捩慊潣ൢ䌊㩣 戠畤湮䁥捩湯攭杮湩敥獲挮浯਍畓橢捥㩴删㩅嘠瑩畲楶湡ⴠ䴠祡䔠瑳浩瑡൥ഊ ਍਍牂捵⁥潦湵⁤⁡潣灵敬洠牯⁥獩畳獥ഺഊ ਍਍㈣′ₖ档湡敧戠汩楬杮焠慵瑮瑩⁹潴␠‰ₖ潭楶杮琠慰歲瀠捡慫敧਍਍㌣‴ₖ档湡敧戠汩楬杮焠慵瑮瑩⁹潴␠‰ₖ潭楶杮琠慰歲瀠捡慫敧਍਍㌣‷ₖ档湡敧戠汩楬杮焠慵瑮瑩⁹潴␠‰ₖ潭楶杮琠慰歲瀠捡慫敧਍਍㔣‹ₖ癯牥楢汬摥阠猠潨汵⁤敢ㄠⰸ㌶猰൦ഊ⌊ㄱ‷ₖ癯牥楢汬摥阠猠潨汵⁤敢ㄠ㐬㈷晬਍਍㈣㐴阠猠 敥戠汥睯阠挠牯敲瑣挠湯牴捡⁴浡畯瑮椠⁳〲渠瑯㈠‱獡䤠猠慴整൤ഊ⌊㔲‱ₖ癯牥楢汬摥阠礠畯戠汩敬⁤潦⁲㠸慥‬潣瑮慲瑣栠獡㠠收ൡഊ⌊㘲‱ₖ癯牥楢汬摥阠猠潨汵⁤敢ㄠㄬ㘸晬਍਍㈣㈷阠漠敶扲汩敬⁤ₖ桳畯摬戠⁥攱ൡഊ⌊㜲″ₖ癯牥楢汬摥阠猠潨汵⁤敢㌠攱ൡഊ ਍਍桔湡獫ബഊ ਍਍ഠഊ䔊楲⁣楌瑴敬਍਍牐橯捥⁴慍慮敧Ⱳ唠剄਍਍㐵〳䰠䩂䘠敲睥祡‬畓瑩⁥㈱〵਍਍慄汬獡‬塔㜠㈵〴਍਍桐›㜹⸲㜷⸴㔰㈵਍਍硆›㜹⸲㤹⸱ㄴ㌱਍਍ 敃汬›ㄲ⸴㐶⸱㜵ㄶ਍਍睷⹷䑕⹒潣൭ഊ ਍਍牆浯›牅捩吠‮楌瑴敬ഠ匊湥㩴吠敵摳祡‬畊敮ㄠⰵ㈠㄰‰㨴ㄲ倠്吊㩯愠潲灬䁨瑮硥潣⹮潣㭭娠捡⁨畆楳楬牥⠠智獵汩敩䁲瑮硥潣⹮潣⥭※楎正䨠捡扯਍捃›摢湵敮楀潣⵮湥楧敮牥⹳潣൭匊扵敪瑣›坆›楖牴癵慩‭慍⁹獅楴慭整਍਍ഠഊ䄊摮敲㩷਍਍ഠഊ䠊癡⁥⁡潣灵敬椠獳敵⁳楷桴琠敨映汯潬楷杮椠整獭ഺഊ ਍਍ㄣ㌲阠漠敶扲汩敬⁤ₖ桴獩眠汩敢愠摤敲獳摥椠桴⁥敮瑸䌠ⱏ戠瑵眠⁥慣楢 汬漠敶⁲楷桴畯⁴湡愠灰潲敶⁤佃爠杩瑨渠睯മഊ⌊㈱‵ₖ癯牥楢汬摥阠琠楨⁳慷⁳湯洠⁹楬瑳氠獡⁴潭瑮⁨潴ₖ敷渠敥⁤潴爠獥汯敶琠楨⁳癯牥条⹥਍਍㈣㐴阠漠敶扲汩敬⁤ₖ潹⁵楢汬摥映牯㈠攲ⱡ挠湯牴捡⁴慨⁳ㄲ慥਍਍㈣ㄵ阠漠敶扲汩敬⁤ₖ潹⁵楢汬摥映牯㠠攸ⱡ挠湯牴捡⁴慨⁳㘸慥਍਍㈣㤶阠漠敶扲汩敬⁤ₖ潮⁴畳敲栠睯䤠洠獩敳⁤桴獩漠敮氠獡⁴潭瑮ⱨ戠瑵礠畯愠敲漠敶⁲湯琠敨挠湯牴捡⁴畱湡楴祴愠摮琠楨⁳畤瑣戠湡獩渠瑯挠浯汰 瑥⁥敹⁴瀨湥楤杮瀠敩獲⸩਍਍ഠഊ ਍਍牅捩䰠瑩汴൥ഊ倊潲敪瑣䴠湡条牥‬䑕൒ഊ㔊㌴‰䉌⁊牆敥慷ⱹ匠極整ㄠ㔲രഊ䐊污慬ⱳ吠⁘㔷㐲രഊ倊㩨㤠㈷㜮㐷〮㔵ലഊ䘊㩸㤠㈷㤮ㄹ㐮ㄱളഊ䌊汥㩬㈠㐱㘮ㄴ㔮㘷റഊ眊睷售剄挮浯਍਍ഠഊ䘊潲㩭䄠摮敲⁷潒灬⁨浛楡瑬㩯牡汯桰湀整捸湯挮浯⁝਍敓瑮›潍摮祡‬畊敮ㄠⰴ㈠㄰‰㨷㤳倠്吊㩯䔠楲⁣⹔䰠瑩汴൥䌊㩣丠捩慊潣㭢稠捡晫※湡牯൤匊扵敪瑣›楖牴癵慩‭慍⁹獅楴慭整਍਍ഠഊ䔊楲Ᵽ栠牥 ⁥獩漠牵䴠祡攠瑳浩瑡⁥潦⁲潹牵爠癥敩⹷†桔⁥湯祬琠楨杮琠慨⁴⁉瑳汩敮摥琠潭楤祦椠⁳桴⁥浡畯瑮丠䍔栠獡戠敥慰摩琠慤整‬畢⁴桴獩眠汩瑡氠慥瑳朠瑥礠畯猠慴瑲摥漠敲楶睥湩⁧桴⁥畱湡楴楴獥മഊ吊慨歮ⱳ਍਍ഠഊ䄊摮敲⁷⹄删汯桰਍਍潎瑲⁨敔慸⁳潃瑮慲瑣湩൧ഊ㐊㤹‹敋汬牥䠠獡敬⁴摒മഊ䬊汥敬Ⱳ吠⁘㘷㐲സഊ⠊⥏㠠㜱㐭〳㤭〵രഊ⠊⥆㠠㜱㐭〳㤭〲ഷഊ⠊⥍㠠㜱㠭㤱〭〷ളഊ ਍਍