Nick, per our phone conversation, we discussed our concern with an upcoming JRJ claim for a fill item to be added prior to remobilizing for phase 3 paving. The concern is that there is not an embankment item for any the fill; there is a “street excavation” item, but it doesn’t account for the fill previously completed and upcoming. As you know, phase 3 is currently awaiting JRJ’s scope to complete dirt work, lime and paving, but we must resolve this issue immediately to continue as planned. Right now, it is way too saturated for them to move in from all of this past rain and snow or else they would have started two weeks ago. Right now, we have asked JRJ to formalize a letter and claim so we can forward on for approval to keep production moving. Marty says that he will complete the letter this week as of last week and again this afternoon… I already spoke with Clay as well to inform him of this as well. Thanks, Andrew D. Rolph North Texas Contracting 4999 Keller Haslet Rd. Keller, TX 76248 (O) 817-430-9500 (F) 817-430-9207 (M) 817-819-0703