Eric The grading work that Drew is trying to get JRJ to perform around the storm inlet down by Marsh Lane was not indicated on the original “approved for construction” plans. It appears as though it was added per the changes that were issued on December 14, 2009 by Joel. I have asked Marty to do a quick takeoff on the dirt quantity for this area so that we can get a change in quantity for “Unclassified Excavation” change order going so that they can complete this work. Please let me know if you agree / disagree with this or have any other comments regarding it. I have also attached the two drawings as reference for you. Thanks Andy Andrew D. Nord North Texas Contracting | Estimator 4999 Keller Haslet Rd. Keller, TX 76248 Phone: 817.430.9500 Fax: 817.430.9207 Cell: 817.819.4117