Gentlemen, We are wrapping up the fitness center this week and will be ready for a CO as the first turn of apartments arrive at Vitruvian Park at the end of this month. I have contacted both building inspection and the fire department, and neither have an issue with giving a CO for this portion of the project. (Permit # 14353) The sidewalks at the front of the project (see attached) is the issue that I know you will be concerned about. North Texas is installing conduit and drilling for the pole lights on Ponte Avenue and we will then follow directly behind them with sidewalks and pavers. We are estimating that to happen the first week of March. With Ponte Ave not being complete, this only being used by residents, and still having a main point of entry through the leasing office, there are still two of three emergency exits immediately available. Will you have any outstanding issues that would keep a CO from being issued here? Tanner Whitson Andres Construction Services 3789 Brookhaven Club Dr. Addison, TX 75001 office: 972.241.5042 cell: 214.240.2658 fax: 972.241.5044 www.andresconstruction.com The information contained in this email message is privileged and confidential information intended only for the use of the individual or entity named above. If the reader of this message is NOT the intended recipient or the employee or agent of the intended recipient, you are hereby notified that any dissemination, distribution, or copying of this communication is strictly prohibited. If you have received this communication in error, please notify the sender to arrange for the return of the documents.