New RFI No. 21 As of 22-Jul-2009 12:03 PM CT Vitruvian Infrastructure Phase 1B 4010 Marsh Lane Addison, Texas 75001 Project Number: 1308B Status: Outstanding Subject Existing 8" water line conflict with 6x5' RCB Reason Code None Question The existing 8" water line that we are to remove at a later date is in conflict with the 6x5' RCB currently being installed up to station 5+15.93 on line SD-A1 as shown on sheet 33. Proposed Solution NTC proposes to slightly raise this existing water line using 4 - 11-1/4 bends (with Thrust blocking) to allow the 6x5' RCB to be installed on grade. Please note that there is already a pay item for "lowering the existing 8" main" (item 154). Please advise. Attached Files (none) Section: 2 - Sitework Int. Tracking #: Days Elapsed: 0 From: Andrew Rolph Originated: 22-Jul-2009 12:03 PM CT To: Jennifer Haynes, PE (First Recipient) Requested By: 25-Jul-2009 11:55 AM CT Copy to: Andrew Rolph Andy Nord Joel Massey Nick Jacob Jennifer Haynes, PE Wade Geistweidt Zach Fusilier Bruce Dunne Craig Benckendorf Clay Barnett Additional Info Proposed Solution Impact Critical Path? Yes Cost Change: Cost Increase of US $4,000 Time Change: None Discipline Code: Civil Drawing Numbers: 33 Needs Drawing Change? N/A History (Chronological Order) No history to display. Final Response (Closing) This item is still open. No final response to display. .................................................................................. Copyright (c) 1999-2009, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - Blueprint for e-Management