New RFI No. 26 As of 12-Aug-2009 1:14 PM CT Vitruvian Infrastructure Phase 1B 4010 Marsh Lane Addison, Texas 75001 Project Number: 1308B Status: Outstanding Subject 6" water main needs to be raised to avoid conflict with the 6x5 RCB Reason Code None Question There is an existing 8" water main running north-south at about station 23+90 on sheet 57 that is in conflict with our proposed 6x5 RCB (line SD-A1). The existing water main is currently right underneath the existing 66" RCP line that just recently demolished. Proposed Solution NTC proposed to raise the existing water main to avoid conflicting with the RCB installation. We are proposing to raise the line rather than lower it b/c it will soon be abandoned and there is ample cover still above the box. As before, there is already an item for this additional work (item 154). Please advise if we are to proceed. Attached Files (none) Section: 2 - Sitework Int. Tracking #: Days Elapsed: 0 From: Andrew Rolph Originated: 12-Aug-2009 1:14 PM CT To: Jennifer Haynes, PE (First Recipient) Requested By: 15-Aug-2009 1:03 PM CT Copy to: Andrew Rolph Andy Nord Joel Massey Nick Jacob Jennifer Haynes, PE Wade Geistweidt Zach Fusilier Bruce Dunne Craig Benckendorf Clay Barnett Additional Info Proposed Solution Impact Critical Path? Yes Cost Change: Cost Increase of US $4,000 Time Change: None Discipline Code: Civil Drawing Numbers: 57 Needs Drawing Change? No History (Chronological Order) No history to display. Final Response (Closing) This item is still open. No final response to display. .................................................................................. Copyright (c) 1999-2009, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - Blueprint for e-Management