New RFI No. 35 As of 29-Dec-2009 3:24 PM CT Vitruvian Infrastructure Phase 1B 4010 Marsh Lane Addison, Texas 75001 Project Number: 1308B Status: Outstanding Subject Sanitary line SS-B3 conflict with 5x5 box Reason Code None Question Sanitary line SS-B3 as shown on sheet 69 shows to end at station 0+21, just at the edge of the proposed 5x5 box culvert. The current design has the cleanout stub running across the grade for the proposed box. Per our phone conversation, the proposed 5x5 box culvert running perpendicular to SS-B3 is a temporary storm line. If this is true, NTC recommends moving the end and plug back to station 0+19, and shifting the cleanout back before the box as well. Please advise. Proposed Solution NTC recommends moving the end and plug back to station 0+19, and shifting the cleanout back before the box. Attached Files (none) Section: 2 - Sitework Int. Tracking #: Days Elapsed: 0 From: Andrew Rolph Originated: 29-Dec-2009 3:24 PM CT To: Jennifer Haynes, PE (First Recipient) Requested By: 1-Jan-2010 3:11 PM CT Copy to: Andy Nord Joel Massey Nick Jacob Jennifer Haynes, PE Wade Geistweidt Bruce Dunne Craig Benckendorf Clay Barnett Additional Info Proposed Solution Impact Critical Path? Yes Cost Change: None Time Change: None Discipline Code: Civil Drawing Numbers: 69 Needs Drawing Change? No History (Chronological Order) No history to display. Final Response (Closing) This item is still open. No final response to display. .................................................................................. Copyright (c) 1999-2009, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - Blueprint for e-Management