Dear Projectmates user: This is a reminder for RFI # 10 . The text of the original item appears below. === RFI # 10 ===================================================== PROJECT NAME: Vitruvian Infrastructure Phase 1B DATE SUBMITTED: 6/17/2009 DATE REQUESTED BY: 6/20/2009 SPECIFICATION SECTION: 2 - Sitework SUBJECT: ATMOS 2" gas service line in conflict with UGE manhole 16+60 QUESTION: On sheet 76, the plans depict a 6" Gas line running along the southmost lane of Vitruvian; However, there is also a 2" gas main running off of it and across Vitruvian to the Garden Oak Apartments in conflict with our proposed 8E6 centerline and manhole at station 16+60. -------------------------------------------------------------------------- PROPOSED SOLUTION: NTC recommends the Town of Addison have ATMOS Energy relocate thier existing gas service line to not conflict with our proposed water, sewer, storm, and UGE lines. Please note that ForceCon has just hit this service line as it was not marked or depicted on the plans. Atmos Energy currently has the line clamped and exposed as of 10 AM this morning. To respond to the RFI, visit http://udr.projectmates.com, login for the project and then click on the "Const Mgmt" icon. To view this and other items, login to your project at http://udr.projectmates.com ***************************************** Projectmates Collaboration Server Blueprint for e-Management. *****************************************