Dear Projectmates user: This is a reminder for RFI # 32 . The text of the original item appears below. === RFI # 32 ===================================================== PROJECT NAME: Vitruvian Infrastructure Phase 1B DATE SUBMITTED: 12/1/2009 DATE REQUESTED BY: 12/4/2009 SPECIFICATION SECTION: 2 - Sitework SUBJECT: Tri-Dal fire hydrant needs to lowered QUESTION: The exising fire hydrant shown on sheet 60 in the Park area parking lot needs to be lowered by 6". -------------------------------------------------------------------------- PROPOSED SOLUTION: Because this hydrant is a 5'0 standard bury, NTC will need to install a new 4'6" bury hydrant. Please advise as this is per Clay Barnett and will be a quantity overrun. See adjustments if approved: Item #155 FIRE HYDRANT ASSEMBLY 1 EA @ 2,500.00 Item # 137 RMV & SLVG EXIST FIRE HYDRANT ASSEMBLY @ 1 EA 500.00 To respond to the RFI, visit http://udr.projectmates.com, login for the project and then click on the "Const Mgmt" icon. To view this and other items, login to your project at http://udr.projectmates.com ***************************************** Projectmates Collaboration Server Blueprint for e-Management. *****************************************