Response to RFI No. 23 As of 20-Aug-2009 4:30 PM CT Vitruvian Infrastructure Phase 1B 4010 Marsh Lane Addison, Texas 75001 Project Number: 1308B Status: Complete Subject 6" Dom Meter Vault location Reason Code None Question The existing 6" gas main running perpendicular to the proposed 6" domestic meter and vault (show at station 13+15.22 on sheet 56) is in conflict with the proposed vault location. Proposed Solution NTC proposes to move the vault location towards the new building by 3' from its proposed center at station 13+15.22 to avoid the existing gas main. Please advise. Attached Files (none) Section: 2 - Sitework Int. Tracking #: Days Elapsed: 15 From: Andrew Rolph Originated: 5-Aug-2009 1:21 PM CT To: Jennifer Haynes, PE (First Recipient) Requested By: 8-Aug-2009 12:00 AM CT (Original 8-Aug-2009 1:14 PM CT) Copy to: Andrew Rolph Andy Nord Joel Massey Nick Jacob Jennifer Haynes, PE Wade Geistweidt Zach Fusilier Bruce Dunne Craig Benckendorf Clay Barnett Additional Info Proposed Solution Impact Critical Path? Yes Cost Change: None Time Change: None Discipline Code: Civil Drawing Numbers: 56 Needs Drawing Change? Yes History (Chronological Order) Type Response Billable n/a Memo We do not agree with the NTC proposal to shift the vault closer to the building. This will create other conflicts with the proposed gas line. This vault is an issue with the proposed street scape. We will get the current street scape design from Kevin Sloan Studio and look at where the vault must be installed. Attached Files (none) From: Joel Massey Sent: 5-Aug-2009 4:08 PM CT To: Andrew Rolph Requested By: 8-Aug-2009 12:00 AM CT Copy to: Andrew Rolph Andy Nord Joel Massey Nick Jacob Jennifer Haynes, PE Wade Geistweidt Zach Fusilier Bruce Dunne Craig Benckendorf Clay Barnett Final Response (Closing) Response Revised drawings showing the P1S water meter vault location have been uploaded. A Detailed Plan for the Phase 1 South Meter Vault is attached. The meter vault is in a very tight location and the detailed plan shows the four corner coordinates and elevations for the water meter vault installation. Billable n/a Attached Files P1S_Meter_Plan.pdf From: Joel Massey Sent: 20-Aug-2009 4:30 PM CT To: Andrew Rolph Copy to: Andrew Rolph Junior Rojas Jules Roberts Andy Nord Joel Massey Robyn Jacobson Nick Jacob Steven Hines Jennifer Haynes, PE Wade Geistweidt Zach Fusilier Bruce Dunne Matt Brendel Craig Benckendorf Clay Barnett .................................................................................. Copyright (c) 1999-2009, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - Blueprint for e-Management