Response to RFI No. 25 As of 13-Aug-2009 3:38 PM CT Vitruvian Infrastructure Phase 1B 4010 Marsh Lane Addison, Texas 75001 Project Number: 1308B Status: Outstanding Subject Energizing new 12" line Reason Code None Question In order for NTC to energize the new water line W-A and finish the fill for the subgrade near Ponte, we will need to raise the existing valve stacks as we fill to not cover. This is also crucial to ensure we have the proper centerloading on the pipe to handle the pressure test. This has also become more urgent since the new Andres building is now pushing for the 6" tie in for fire protection. Proposed Solution NTC proposed to add valve riser extentions to the stems and boxes in order to maintain the needed functionality of the valves during the tie ins and different shutdowns. Please advise as this will be an increase in cost. Attached Files (none) Section: 2 - Sitework Int. Tracking #: Days Elapsed: 1 From: Andrew Rolph Originated: 12-Aug-2009 1:03 PM CT To: Jennifer Haynes, PE (First Recipient) Requested By: 15-Aug-2009 12:00 AM CT (Original 15-Aug-2009 11:04 AM CT) Copy to: Andrew Rolph Andy Nord Joel Massey Nick Jacob Jennifer Haynes, PE Wade Geistweidt Bruce Dunne Craig Benckendorf Clay Barnett Additional Info Proposed Solution Impact Critical Path? Yes Cost Change: Yes, may be Time Change: None Discipline Code: Civil Drawing Numbers: 56 Needs Drawing Change? Yes History (Chronological Order) Type Response Billable n/a Memo Andrew, we do not follow what you are saying. What specific water valves are you speaking of. The proposed valves are paid to be installed and then paid to be adjusted for final pavement grade. The existing water line and valves will be removed once the new line is in service. The Andres building water taps (fire and domestic) are existing but need to be connected. The water vault location issue is holding up the domestic but the fire connection should be able to be completed. We do not see a need for additional costs. Attached Files (none) From: Joel Massey Sent: 13-Aug-2009 3:38 PM CT To: Andrew Rolph Requested By: 15-Aug-2009 12:00 AM CT Copy to: Andrew Rolph Andy Nord Joel Massey Nick Jacob Jennifer Haynes, PE Wade Geistweidt Bruce Dunne Craig Benckendorf Clay Barnett Final Response (Closing) This item is still open. No final response to display. .................................................................................. Copyright (c) 1999-2009, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - Blueprint for e-Management