Response to RFI No. 40 As of 2-Apr-2010 10:44 AM CT Vitruvian Infrastructure Phase 1B 4010 Marsh Lane Addison, Texas 75001 Project Number: 1308B Status: Complete Subject Crosswalks Reason Code None Question There is an obvious crosswalk placement issue between the phase 2 and 3 paving paver leave outs. We had JBI produce an as-built and superimpose the proposed crosswalk sections (see attached). Most of the crosswalks are very close to proposed except for the one near 22+81. Please review and let's open this up for discussion ASAP as JRJ has intentions to pour this phase 3 paving tomorrow and Thursday. Proposed Solution Attached Files Vitruvian - JRJ crosswalk as-built.pdf Section: 3 - Concrete Int. Tracking #: Days Elapsed: 10 From: Andrew Rolph Originated: 23-Mar-2010 1:34 PM CT To: Eric Little (First Recipient) Requested By: 26-Mar-2010 12:00 AM CT (Original 26-Mar-2010 1:02 PM CT) Copy to: Andrew Rolph Andy Nord Joel Massey Eric Little Nick Jacob Steven Hines Wade Geistweidt Zach Fusilier Bruce Dunne Miles Britt Craig Benckendorf Clay Barnett Additional Info Proposed Solution Impact Critical Path? Yes Cost Change: None Time Change: None Discipline Code: Civil Drawing Numbers: 22 Needs Drawing Change? No History (Chronological Order) Type Routed Billable n/a Memo Bruce, Please review and respond to this RFI. Attached Files (none) From: Eric Little Sent: 1-Apr-2010 3:01 PM CT To: Bruce Dunne Requested By: 26-Mar-2010 1:02 PM CT Copy to: Andrew Rolph Joel Massey Nick Jacob Wade Geistweidt Zach Fusilier Miles Britt Clay Barnett Type Response Billable n/a Memo The crosswalk at Station 22+81 was incorrectly installed as indicated by the as-built survey. The concrete panels on each side of the incorrectly located crosswalk will need to be removed, the crosswalk correctly located, and the street panels repoured accordingly. Attached Files (none) From: Bruce Dunne Sent: 2-Apr-2010 9:43 AM CT To: Eric Little Requested By: 26-Mar-2010 12:00 AM CT Copy to: Andrew Rolph Joel Massey Nick Jacob Wade Geistweidt Zach Fusilier Miles Britt Clay Barnett Final Response (Closing) Response Andrew - see directions from ICON. This RFI is officially closed. Billable n/a Attached Files (none) From: Eric Little Sent: 2-Apr-2010 10:44 AM CT To: Andrew Rolph Copy to: Joel Massey Nick Jacob Bruce Dunne Miles Britt Clay Barnett .................................................................................. Copyright (c) 1999-2010, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - Blueprint for e-Management