Response to RFI No. 44 As of 22-Apr-2010 7:36 AM CT Vitruvian Infrastructure Phase 1B 4010 Marsh Lane Addison, Texas 75001 Project Number: 1308B Status: Outstanding Subject 6" sewer service line for Lemmons Company. Reason Code None Question The existing 6" sanitary sewer service line shown to cross our proposed line around station 23+20 is in conflict. This line intersects our proposed line by only 2" difference in the flowlines. Proposed Solution NTC proposes to tie this existing service line into our new line by using a typical service line 8x6" gasketed SDR-35 PVC WYE. Please advise if this is acceptable. I met with Dave Wilde in the field and he agreed with this proposed solution. Attached Files (none) Section: 2 - Sitework Int. Tracking #: Days Elapsed: 1 From: Andrew Rolph Originated: 21-Apr-2010 5:09 PM CT To: Eric Little (First Recipient) Requested By: 24-Apr-2010 12:00 AM CT (Original 24-Apr-2010 5:03 PM CT) Copy to: Andrew Rolph Andy Nord Joel Massey Eric Little Nick Jacob Wade Geistweidt Zach Fusilier Bruce Dunne Craig Benckendorf Clay Barnett Additional Info Proposed Solution Impact Critical Path? Yes Cost Change: None Time Change: Yes, may be Discipline Code: Civil Drawing Numbers: 69 Needs Drawing Change? No History (Chronological Order) Type Response Billable n/a Memo I agree with the proposed solution. Attached Files (none) From: Joel Massey Sent: 22-Apr-2010 7:36 AM CT To: Andrew Rolph Requested By: 24-Apr-2010 12:00 AM CT Copy to: Andy Nord Joel Massey Eric Little Nick Jacob Wade Geistweidt Zach Fusilier Bruce Dunne Craig Benckendorf Clay Barnett Final Response (Closing) This item is still open. No final response to display. .................................................................................. Copyright (c) 1999-2010, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - The Capital Project Management Software