Response to RFI No. 45 As of 4-May-2010 10:48 AM CT Vitruvian Infrastructure Phase 1B 4010 Marsh Lane Addison, Texas 75001 Project Number: 1308B Status: Outstanding Overdue Subject TOA "mini park" paver semi circle near Marsh Lane Reason Code None Question From station 1+98 to 2+24, there is an existing semi-circle pavement that was to be tied into our new curbline, currently in conflict. After field meetings, we all decided that we would later price re-working the concrete and pavers. Please provide an exhibit for NTC to price if this area is to be re-worked under the 1B contract. Proposed Solution Attached Files (none) Section: 3 - Concrete Int. Tracking #: Days Elapsed: 12 From: Andrew Rolph Originated: 22-Apr-2010 5:26 PM CT To: Eric Little (First Recipient) Requested By: 25-Apr-2010 5:19 PM CT Copy to: Andrew Rolph Andy Nord Joel Massey Eric Little Nick Jacob Wade Geistweidt Zach Fusilier Bruce Dunne Craig Benckendorf Clay Barnett Additional Info Proposed Solution Impact Critical Path? No Cost Change: Yes, may be Time Change: None Discipline Code: N/A Drawing Numbers: 19 Needs Drawing Change? Yes History (Chronological Order) Type Routed Billable n/a Memo Joel, Please provide a sketch to correct this issue. Attached Files (none) From: Eric Little Sent: 4-May-2010 10:48 AM CT To: Joel Massey Requested By: 25-Apr-2010 5:19 PM CT Copy to: Andrew Rolph Nick Jacob Zach Fusilier Bruce Dunne Clay Barnett Final Response (Closing) This item is still open. No final response to display. .................................................................................. Copyright (c) 1999-2010, Systemates, Inc. View the User Agreement for legal restrictions and terms of use applicable to this site. Use of this site signifies your agreement to the terms of use specified in the User Agreement. Projectmates - The Capital Project Management Software