Please see the attached photo of the area under Bella Ln. It appears that you have the same issue on the south side as the north in regard to the area that Austin excavated for their bridge construction. The material is too loose and saturated to perform any type of compaction without building another ramp for access into the creek, excavating the material, and importing dry material. Thanks, Jamie Voris Project Manager North Texas Contracting Cell: 817-819-0377 Fax: 817-430-9207 4999 Keller-Haslet Road Keller, TX 76248