Clay, Here is the Vit Park Phase 1C – July Pay App. Thanks, Eric From: Eric T. Little Sent: Wednesday, August 03, 2011 3:23 PM To: 'Jennifer Haynes'; 'wgeistweidt@kleinfelder.com' Cc: Nick Jacob Subject: RE: July 2011 Pay Application Here are my questions: #64 – need Wade to verify the 182lf of 6” PVC was installed. #175, 176, 177 and 180 – I have not seen any furniture installed on site or stored onsite. Are you trying to bill for stored materials? #285, 287 – Your billing 100%, but the handrails are not complete yet. #CO2-25/26 – why aren’t you billing these two items out? #CO5-2 – the fish habitats are not fixed yet. Take back to 0 this month. Everything else looks good. Thanks, Eric From: Jennifer Haynes [mailto:jennifer@ntexcon.com] Sent: Friday, July 29, 2011 2:51 PM To: Eric T. Little Subject: July 2011 Pay Application Eric, Please find attached the Pay Application. Thank you, Jennifer M. Haynes, P.E. North Texas Contracting, Inc. (214) 808-2821 cell