Below is Icon’s proposed scope for additional services. It was reduced by $45k from the last proposal and is more in line with what I believe is needed to finish the project. Please let me know your thoughts. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Bruce Dunne [mailto:bdunne@icon-engineers.com] Sent: Tuesday, June 14, 2011 10:35 AM To: Clay Barnett Subject: RE: Vitruvian Park - Change in Scope and Fee #5 As-Built Surveys $ 7,500. LOMR $ 32,000. Landscape $ 25,000. Structural $ 7,500. Electrical $ 7,500. Civil $ 20,000. Record Drawings $ 5,000. Reimbursables $ 5,000. _______ Total Estimated Fees $ 109,500. These estimated fees cover work involved with the completion of the Park, the extension of Vitruvian Way to Spring Valley Road, and the extension of Ponte Avenue across the bridge, and assumes that this work will be completed by the scheduled invoice on 9/10/11. Keep in mind, except for the Surveys and LOMR, everything else is invoiced on an hourly basis and is not Lump Sum, so if the time is not spent, the money is not paid. I would prefer not to come back to you again in three months and have to ask for more money. From: Clay Barnett [mailto:cbarnett@addisontx.gov] Sent: Tuesday, June 14, 2011 9:44 AM To: Bruce Dunne Subject: RE: Vitruvian Park - Change in Scope and Fee #5 Bruce, Our preference is that items that come up as described below would be taken from that department’s budget as opposed to using capital project funds for those kinds of issues. Please tailor the proposal to get us through the completion of the project and we can visit those kinds of issues on a case-by-case basis once the projects are complete. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Bruce Dunne [mailto:bdunne@icon-engineers.com] Sent: Tuesday, June 14, 2011 9:41 AM To: Clay Barnett Subject: RE: Vitruvian Park - Change in Scope and Fee #5 I can. As I told you, it should be considerably less than the total dollar amount of the extra services provided, but on the other hand this will probably be the last CSF for the project, and if the work drags on and on (as it will long past August), I will not get another chance for reimbursement, so I want to make sure there is sufficient funding for all the little “extras” that are sure to come up, i.e. site electrical plans for Special Events, etc. etc. From: Clay Barnett [mailto:cbarnett@addisontx.gov] Sent: Tuesday, June 14, 2011 9:34 AM To: Bruce Dunne Subject: RE: Vitruvian Park - Change in Scope and Fee #5 Bruce, Although it is helpful to have the history of the overages, we need to take to council what we anticipate will be the expenses associated with the Phase 1C (the park) and Phase 1E (Vitruvian Way Extension). As you recall Phase 2 (Bella Lane) has a separate contract. Could you send us a schedule of the anticipated expenses through the completion of these two projects, which are currently scheduled for completion in August? Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857 From: Bruce Dunne [mailto:bdunne@icon-engineers.com] Sent: Wednesday, June 08, 2011 12:52 PM To: Clay Barnett Subject: FW: Vitruvian Park - Change in Scope and Fee #5 Hey Clay – I never heard back from you on this. Can you give me a status report? From: Bruce Dunne Sent: Monday, May 23, 2011 9:44 AM To: 'Clay Barnett' Cc: 'Nancy Cline' Subject: Vitruvian Park - Change in Scope and Fee #5 Good morning Clay. As you will recall, we submitted a “change in scope and fee (CSF)” request to the Town of Addison last September for additional services for Vitruvian Park, the greater part of which was related to the bridge re-design and the additional bid packages that were prepared for this project. A copy of this CSF is attached. Also attached is a detailed breakdown by month, task and man-hours associated with this request for extra services to date. Ultimately, this CSF was withdrawn from the scheduled council meeting as we agreed to postpone this until a later date. As of today, we have less than $6,000 remaining under our contract with the Town, so we would like to request that we proceed with this change order before next month’s billing period. Thanks. BRUCE F. DUNNE, P.E. President icon Consulting Engineers, Inc. Bicentennial Financial Center 250 W. Southlake Blvd., Suite 117 Southlake, Texas 76092 Phone: (817) 552-6210 Fax: (817) 552-3126 Mobile: (817) 707-9711 ************************************************************ This e-mail and any files or attachments transmitted with it contain Information that is confidential and privileged. This document may contain Protected Health Information (PHI) or other information that is intended only for the use of the individual(s) and entity(ies) to whom it is addressed. If you are the intended recipient, further disclosures are prohibited without proper authorization. If you are not the intended recipient, any disclosure, copying, printing, or use of this information is strictly prohibited and possibly a violation of federal or state law and regulations. If you have received this information in error, please delete it and notify Hamid Khaleghipour at 972-450-2868 immediately. Thank you. ************************************************************ ************************************************************ This e-mail and any files or attachments transmitted with it contain Information that is confidential and privileged. This document may contain Protected Health Information (PHI) or other information that is intended only for the use of the individual(s) and entity(ies) to whom it is addressed. If you are the intended recipient, further disclosures are prohibited without proper authorization. If you are not the intended recipient, any disclosure, copying, printing, or use of this information is strictly prohibited and possibly a violation of federal or state law and regulations. If you have received this information in error, please delete it and notify Hamid Khaleghipour at 972-450-2868 immediately. Thank you. ************************************************************