FYI -----Original Message----- From: Eric T. Little Sent: Friday, December 03, 2010 2:34 PM To: 'Walker, Standridge M SWF'; 'Botorino@tceq.state.tx.us'; 'stan.okie@gmail.com' Cc: Nick Jacob; Tom Lamberth; Deiadra Burns Subject: RE: Vitruvian Park 2007-00583 - WEEKLY STATUS REPORT - Week Ending 03Dec2010 Stan/Bismarck: Attached is the report of the current status of the project as. The weather has been great this week and we anticipate completion of the excavation work and install of the new cofferdam in Reach 2 today and demo of the existing box culvert bridge tomorrow. The current weather forecast shows very little chance for precipitation for the next 10 days. Let me know if you have any questions or concerns. Thanks, Eric Little Project Manager, UDR 5430 LBJ Freeway, Suite 1250 Dallas, TX 75240 Ph: 972.774.0552 Fx: 972.991.4113 Cell: 214.641.5761 www.UDR.com