Clay, Per our phone conversation we wanted to make you aware of a schedule conflict between the well construction and Bella Lane paving. I've attached a schematic showing the minimum construction staging area for the well. The project schedule shows paving for Bella Lane in July. Any finished paving would likely be damaged during the well construction. Lisa -------------------------- Sent using BlackBerry ________________________________ From: Gary Witt To: Lisa Larson Sent: Wed May 11 06:51:40 2011 Subject: Schematic Drawing Please See Attached G.(Witt) Witterstaetter Technician II 1826 Kramer Lane, Suite M Austin, Texas 78758 o| 512.926.6650 d| 512.491.4615 f | 512.833.5058