Nick, The pay application has been signed by NTC. Please check the following: · The formula in Cell J320 was replaced with a number in the spreadsheet that Eric sent to me. I assumed the number was supposed to be in the current quantities column instead of the current amount. Please verify. · The price for CO6-12 in the change order is $10.46 as opposed to the $10.45 contained in the spreadsheet. · It indicated an overage in Item CO4-5. I assumed this is a typo and reduced it to 1. Please verify. · The contract total appears to be incorrect in the spreadsheet. Please verify. If everything looks good, please sign it and send it to me. If you have any questions, please let me know. Thanks, Clay Barnett, P.E. Town Engineer Town of Addison 16801 Westgrove Drive Addison, TX 75001-2818 Office: (972) 450-2857